The Parliamentary Committee on Transport, Communications and E-Governance announced (19 November 2026) that the completion rate of the Nasiriyah International Airport project in Dhi Qar Governorate has reached 71 percent. Delivery had been scheduled for 2025.
The Governor of Dhi Qar, Haider al-Husainawi, said a committee delegation, accompanied by the Director General of Air Navigation, visited the airport to review the progress of work and preparations for its opening. He added that the local government has met its commitments, including connecting road, water and sewage networks, and that the remaining obstacles relate to the implementing company and the ministries concerned. Foremost among them is completing the electricity file and installing a dedicated power station for the airport.
The committee chair, Muna al-Gharabi, said the committee held an extended meeting with the local government, a Ministry of Transport delegation, and the consulting and implementing companies to discuss the causes of the delay. She said the main technical observations were a shortage of firefighting systems, the clinic, and some infrastructure requirements. She added that the committee decided to hold a joint meeting bringing together the ministries of Transport, Electricity and Planning, the Civil Aviation Authority and the General Secretariat of the Council of Ministers, along with the consulting and implementing parties, to settle the outstanding files.
For his part, Member of Parliament Razzaq Muhaibis al-Saadawi said the main obstacles are that electric power has not been connected to the airport and that navigation equipment from European origins has arrived late. He said the committee will follow up the energy file with the local government and the Ministry of Electricity, and will coordinate with the implementing company, the Ministry of Transport and the General Secretariat of the Council of Ministers to speed up the shipping of navigation and ground equipment.
This comes after the project passed its scheduled delivery date, according to Al-Iqtisad News. What was reported from the committee did not include a new opening date.
Electricity and navigation equipment are two items on which the airport's operation depends, and both rely on parties outside the local government: the Ministry of Electricity on one side, and an equipment shipment from Europe on the other. For this reason the 71 percent figure does not measure how close the opening is, and the air gateway that Dhi Qar is waiting for remains contingent on settling these two files.